1. Preparation before installation
Determine the installation site: select a solid, flat, and unobstructed site to ensure that the bearing capacity of the installation ground can meet the requirements.
Prepare installation tools: prepare special tools such as cranes, wire ropes, and pneumatic screwdrivers.
Prepare installation personnel: professional engineers and technicians are required to install to ensure that the installation process is safe and reliable.
2. Precautions during installation
Fix the base: fix the base on the ground.
Lift the silo: lift the silo with a crane, place it vertically on the base, adjust the position, and ensure that the silo is vertical to the base.
Install the pneumatic system: perform an air tightness test after installing the pneumatic system to ensure that the pneumatic system works properly.
Install accessories: install valves, pipes and other accessories on the silo.
Confirm that the installation is complete: check and confirm that the cement silo has been fully installed as required, and there are no loose parts or air leaks that have not been fixed.