180 commercial concrete mixing station is a large concrete mixing station. Many commercial concrete enterprises will choose this type of equipment. So how to plan the site of 180 commercial concrete mixing station?
1. The overall planning area of 180 commercial concrete mixing station should not be less than 30 mu. Automatic car washing devices should be installed at the main exit of vehicles to effectively clean large freight vehicles such as commercial concrete transport vehicles, sand and gravel transport vehicles, and bulk cement transport vehicles in time; the production area and living area should be separated, and there should be enough area in the station to set up green belts. The station area should be isolated by transparent or green walls, and the height should be ≥2m. Open construction is not allowed.
2. In addition to the production area, the 180 commercial concrete mixing station should be equipped with laboratories, office buildings, parking lots, car wash stations, testing stations, cultural and entertainment facilities and other related facilities.
3.180 commercial concrete mixing station must be reasonably equipped with diversion ditches around and inside to collect sewage to ensure that sewage does not overflow in the station; at least 3 clarification (sedimentation) pools with a single volume of not less than 40m3 should be set up in the station for sewage classification and sedimentation; at least 1 clear water pool with a single volume of not less than 60m3 should be set up, and at least 3 slurry mixing pools with a single volume of not less than 20m3 should be set up to treat and utilize the slurry.
4. If a slurry filter press system is used, the clarification (sedimentation) pool, clear water pool, and slurry mixing pool should be set up according to the requirements of matching equipment.
5. A closed sand and gravel yard with an area of not less than 3,000 m2 should be set up.
6. According to the design of the main building of the 180 commercial concrete mixing station, a special charging area for bulk powder transport vehicles should be reasonably set up, and a semi-enclosed design should be adopted to reduce and isolate the noise during the charging process.
7. The main and secondary lanes should be reasonably set up within the scope of the 180 commercial concrete mixing station according to different vehicles. The width of the main road should not be less than 10 meters, the width of the secondary road should not be less than 8 meters, and the turning radius of the mechanical vehicle road should not be less than 12 meters; and independent sidewalks should be set up to ensure the separation of people and vehicles in the office area. The ground of the station road and the production operation area should be hardened with dust-free cement concrete or asphalt concrete. Take measures to keep the roads in the station clean, and there is no obvious visible dust when vehicles are driving.
8. The unhardened open space in the living area and office area should be greened, and the greening rate of the station shall not be less than 15%, and actively promote the three-dimensional greening of buildings.
The above are the things that need to be paid attention to in the site planning of the 180 commercial concrete mixing station. If you buy our 180 commercial concrete mixing station, we will send technicians to guide you now.